Zone Definition

Wattnet defines zones as distinct geographical areas for which energy generation and exchange data is collected and environmental impact metrics are then calculated.

Spatial Granularity of Zones in Wattnet

To define the spatial granularity of zones, Wattnet primarily relies on existing administrative boundaries and energy market regions, as these are the standard reference points for energy data reporting. Since Wattnet's main data source is ENTSO-E, the following zone definitions are used, reflecting common practice in the European energy market:

Zone Definitions

  • Country: A country is a recognized territorial and political entity. Countries are often used as reporting zones due to the availability of national-level statistics and established regulatory frameworks.
  • Bidding Zone (BZN): A bidding zone is the largest area within which market participants (producers and consumers) submit their offers and bids without being affected by internal grid constraints. It reflects the economic segmentation of the electricity market.
  • Control Area (CTA): A control area is a defined part of the transmission grid for which a specific transmission system operator (TSO) is responsible. The TSO ensures real-time balance between electricity generation and consumption, and maintains grid stability.

Note

More area definitions exist, but they are less commonly used in the context of energy data reporting and more used in grid operation and market coordination. See the ENTSO-E Area List for a comprehensive overview.

Granularity Strategy

Wattnet always aims to use the most spatially granular data available. Therefore, when multiple zone definitions exist for the same geographical area, the smallest available zone is prioritized. For example, if both bidding zone and country-level data are available for a region, bidding zone data will be used.

Each geographical area has an associated EIC code (Energy Identification Code), which uniquely identifies the zone in energy market data. See the EIC code list for reference.

However, data availability and granularity vary across regions, and practical implementation must adapt accordingly. The following examples illustrate these differences.

Regional Examples

Standard cases

  • The majority of European countries (e.g., France, Spain, Poland) are defined as one country, one bidding zone, and one control area. In these cases, all three definitions align perfectly.

Exceptions

Some regions differ due to unique market structures or geopolitical factors:

  • Italy: One country. Multiple bidding zones (North, Central North, Central South, South, Sicily, Sardinia, Calabria). One control area.
    • Bidding zones are used.
  • Sweden: One country. Four bidding zones (North, Central North, Central South, South). One control area.
    • Bidding zones are used.
  • Norway: One country. Five bidding zones (Southeast, Southwest, Central, North, West). One control area.
    • Bidding zones are used.
  • Denmark: One country. Two bidding zones (East and West). One control area.
    • Bidding zones are used.
  • Germany: One country. Bidding zone includes Germany + Luxembourg, 4 control areas (50Hertz, Amprion, TenneT, TransnetBW).
    • No cross-border physical flows data between control areas, so country-level data is used.
    • No data at "country-to-bidding-zone" level between Germany and Denmark (which has two bidding zones). This is taken into account when calculating exchanges.
  • United Kingdom of Great Britain and Northern Ireland & Ireland: Two countries. Two bidding zones. Three control areas.
    • Northern Ireland belongs to the UK politically, but to the Ireland bidding zone.
    • Three control areas: Great Britain, Northern Ireland, and Ireland.
    • Control area data is used. Data exists at "control-area-to-control-area" level.
  • Ukraine: One country. One bidding zone. Two control areas.
    • No control area data available, so country-level data/bidding zone data is used.
  • Russian Federation: One country and one control area. Each has multiple bidding zones (Russia, Kaliningrad).
    • Bidding zones are used.

Conclusion

These examples show how zone definitions often overlap, but are not always perfectly aligned. Wattnet uses the most granular data available, while adapting to the specific market structures and data availability of each region.

Current Zone List

The following table lists the zones currently defined in Wattnet, along with their attributes:

Wattnet Zone Code Zone Name Country Bidding Zone Control Area EIC
AL Albania Yes Yes Yes 10YAL-KESH-----5
AM Armenia Yes Yes Yes 10Y1001A1001B004
AT Austria Yes Yes Yes 10YAT-APG------L
AZ Azerbaijan Yes Yes Yes 10Y1001A1001B05V
BA Bosnia and Herzegovina Yes Yes Yes 10YBA-JPCC-----D
BE Belgium Yes Yes Yes 10YBE----------2
BG Bulgaria Yes Yes Yes 10YCA-BULGARIA-R
BY Belarus Yes Yes Yes 10Y1001A1001A51S
CH Switzerland Yes Yes Yes 10YCH-SWISSGRIDZ
CY Cyprus Yes Yes Yes 10YCY-1001A0003J
CZ Czechia Yes Yes Yes 10YCZ-CEPS-----N
DE Germany Yes No No 10Y1001A1001A83F
DK1 Denmark (West) No Yes No 10YDK-1--------W
DK2 Denmark (East) No Yes No 10YDK-2--------M
EE Estonia Yes Yes Yes 10Y1001A1001A39I
ES Spain Yes Yes Yes 10YES-REE------0
FI Finland Yes Yes Yes 10YFI-1--------U
FR France Yes Yes Yes 10YFR-RTE------C
GB Great Britain No No Yes 10YGB----------A
GE Georgia Yes Yes Yes 10Y1001A1001B012
GR Greece Yes Yes Yes 10YGR-HTSO-----Y
HR Croatia Yes Yes Yes 10YHR-HEP------M
HU Hungary Yes Yes Yes 10YHU-MAVIR----U
IE Ireland No No Yes 10YIE-1001A00010
IT_CALABRIA Italy (Calabria) No Yes No 10Y1001C--00096J
IT_CNORTH Italy (Central North) No Yes No 10Y1001A1001A70O
IT_CSOUTH Italy (Central South) No Yes No 10Y1001A1001A71M
IT_NORTH Italy (North) No Yes No 10Y1001A1001A73I
IT_SARDINIA Italy (Sardinia) No Yes No 10Y1001A1001A74G
IT_SICILY Italy (Sicily) No Yes No 10Y1001A1001A75E
IT_SOUTH Italy (South) No Yes No 10Y1001A1001A788
LT Lithuania Yes Yes Yes 10YLT-1001A0008Q
LU Luxembourg Yes No Yes 10YLU-CEGEDEL-NQ
LV Latvia Yes Yes Yes 10YLV-1001A00074
MD Moldova Yes Yes Yes 10Y1001A1001A990
ME Montenegro Yes Yes Yes 10YCS-CG-TSO---S
MT Malta Yes Yes Yes 10Y1001A1001A93C
MK North Macedonia Yes Yes Yes 10YMK-MEPSO----8
NIE Northern Ireland No No Yes 10Y1001A1001A016
NL Netherlands Yes Yes Yes 10YNL----------L
NO1 Norway (Southeast) No Yes No 10YNO-1--------2
NO2 Norway (Southwest) No Yes No 10YNO-2--------T
NO3 Norway (Central) No Yes No 10YNO-3--------J
NO4 Norway (North) No Yes No 10YNO-4--------9
NO5 Norway (West) No Yes No 10Y1001A1001A48H
PL Poland Yes Yes Yes 10YPL-AREA-----S
PT Portugal Yes Yes Yes 10YPT-REN------W
RO Romania Yes Yes Yes 10YRO-TEL------P
RS Serbia Yes Yes Yes 10YCS-SERBIATSOV
RU Russia No Yes Yes 10Y1001A1001A49F
RU_KGD Russia (Kaliningrad) No Yes Yes 10Y1001A1001A50U
SE1 Sweden (North) No Yes No 10Y1001A1001A44P
SE2 Sweden (Central North) No Yes No 10Y1001A1001A45N
SE3 Sweden (Central South) No Yes No 10Y1001A1001A46L
SE4 Sweden (South) No Yes No 10Y1001A1001A47J
SI Slovenia Yes Yes Yes 10YSI-ELES-----O
SK Slovakia Yes Yes Yes 10YSK-SEPS-----K
TR Turkey Yes Yes Yes 10YTR-TEIAS----W
UA Ukraine Yes Yes No 10Y1001C--00003F
XK Kosovo Yes Yes Yes 10Y1001C--00100H

Temporal Granularity

The temporal granularity in Wattnet refers to the time intervals at which energy generation and exchange data are collected and reported for each defined zone. The same temporal resolution is used to compute environmental impact metrics.

The ENTSO-E Transparency Platform provides data at different temporal resolutions depending on the data type and the specific zone(s) involved. The most common temporal granularities are hourly, 30-minute, and 15-minute intervals. There is no direct mapping between zone definitions and temporal granularities, as these may vary over time.

Wattnet Temporal Granularity Strategy

Wattnet aims to use the most granular useful data available for each zone while ensuring consistency and comparability across all zones. A minimum temporal granularity of 15 minutes is defined for all zones, so all data is processed and reported at this interval.

This approach is possible because ENTSO-E reports average power (in Watts) for each time interval, not total energy (in Watt-hours). Power (W) is an instantaneous or average rate of energy generation or consumption, meaning it is independent of the interval length. Therefore, a value reported as the average power over 1 hour can be applied to shorter intervals (e.g., four 15-minute segments) without inconsistency. In such cases, the same value is repeated across all 15-minute intervals within the hour.

For zones that report data natively at 15-minute intervals, the power values naturally vary every 15 minutes. But for zones with coarser resolutions (like hourly), replicating the reported average power across finer intervals maintains internal consistency and enables uniform 15-minute granularity across the system.

This strategy enables Wattnet to compute standardized and comparable environmental impact metrics at a high temporal resolution (15-minute intervals) for all zones, while preserving data integrity and remaining faithful to the nature of the original data.

Data Files

The zone definition data files used by Wattnet are published at github.com/wattnet/wattnet-data/tree/main/zones.